Constructing the Temporary Bypass
12/3/2018
A temporary bypass is in the process of being constructed since the existing Route 8 NB needs to have a complete concrete deck replacement which includes new joints and parapet curbs for the entire bridge structure.
-
Partial/Full Depth Deck Repairs
10/19/2018
Repairs to the fifty-two (52) year old Route 8 / I-84 interchange in Waterbury, popularly known as the “Mixmaster”, are currently underway. Both temporary and permanent repairs to several of the ten (10) separate bridges that make up the Mixmaster have begun.