-
How do I submit a claim?
Claims for damages and/or personal injuries which occurred within the Route 8/I-84 Mixmaster Rehabilitation Project limits, as a result of some action or inaction of the I-84 Waterbury Project Team, can be submitted by sending written notice that includes the claimant's contact information, a description of the accident given rise to the claim, and a description of damage/personal injuries suffered. For full instructions on submitting a claim, click here. If your incident did not occur within the Route 8/I-84 Mixmaster Rehabilitation Project limits, please see the CTDOTâs webpage with instructions for filing a claim.
-
When will the project be completed?
The estimated completion date is October 2024.
-
When will construction take place?
Allowable periods of construction vary by time of day and day of the week.
- I-84 East and Westbound – closure of one (1) lane at 10:00 p.m. and a second lane at 11:00 p.m. and then all lanes re-opened by 6:00 a.m.;
- Route 8 North and Southbound – closure of one (1) lane at 7:00 p.m. and then all lanes re-opened by 6:00 a.m.;
- Local roads – Monday-Friday, no lane closures between 6:00 a.m.-9:00 a.m. / 3:00 p.m.-6:00 p.m. and Saturday-Sunday, no lane closures between 10:00 a.m.-6:00 p.m.